By Mel Neale
March 31, 2006
We received
the following on March 31, 2006 in the late afternoon. It is the third
change in this schedule of bridge closures.
**** March 31, 2006 ****
New Schedule for Channel Closures
Revised
Notice To Mariners:
The channel
will be restricted or closed at the Bridge of Lions
in St. Augustine according to the following schedule:
| Dates
|
Restriction/Closure
Times |
Comment |
| March
29 -April 6, 2006 |
7:00
am to 1:00 pm & 2:00 pm to 8:00 pm
|
Channel
restricted to 55 feet wide. Full channel openings with 2 hour notice.* |
| April
7, 2006 |
9:00
am to 5:00 pm |
Channel
closed for 8 hours. Full channel openings with 2 hour notice.* |
| April
14, 2006 |
7:00
am to 11:00 am |
Channel
closed for 4 hours. Full channel openings with 2 hour notice.* |
| April
24-27, 2006 |
Full
Closure – 24 hours a day |
Bridge
will be blocking the channel and not functioning. Small craft, less
than 24 feet vertical clearance, will be able to pass under bridge. |
| April
28 - May 12, 2006 |
Intermittent
Closures – 4 hours maximum between 7:00 am and 9:00 pm |
Bridge
blocking channel during installation and testing of controls and balancing.
Three 4 hour closure periods each day with opening provided with 2
hours notice.* |
| *Requests
for a channel opening according to the above schedule should be made
to the Bridge Tender via marine radio on Channel 9. |
For questions
regarding this notice, please call (904) 825-3647. The above schedule
has been approved by the U.S. Coast Guard.
This
information is not to be used for navigation. Consult the latest charts
and Local Notices to Mariners and use prudent seamanship. Any person or
entity that uses this information in any way, as a condition of that use,
agrees to waive and does waive any and all claims which may arise from
that use.